INSTRUCTIONS FOR USE FOR GEBO LIQUID MICRO:
1. Determine the volume of water present in the heating system – see table „water volume in heating systems“.
2. Filters and strainers must be removed.
3. Bring gas-fired boiler system to operating temperature (60 °C). If the operating temperature of 60 °C is not achieved, the duration of the sealing process may extend accordingly (by several days).
4. It is essential to ensure that the circulating pump operates continuously during the sealing process, because the sealant can only reach the damaged area by circulation.
5. Fully open thermostatic valves.
6. Shake Liquid Micro well and add undiluted via the heating filling valve into the heating circuit (1 litre of sealant to 100 litres of water) – see „dosing instruction“.
7. Thoroughly vent circulating pumps and radiators.
8. After a minimum of 24 hours, the gas-fired boiler system can be placed back into normal operation (filters and strainers must be reinstalled).
9. In order to prevent undesirable crystallisation, all working equipment and objects, which have come into contact with the liquid sealants, must be rinsed thoroughly with water.
10. After 4 weeks the gas-fired boiler system must be flushed and filled with fresh water
INSTRUCTIONS FOR USE FOR GEBO LIQUID MICRO:
1. Determine the volume of water present in the heating system – see table „water volume in heating systems“.
2. Filters and strainers must be removed.
3. Bring gas-fired boiler system to operating temperature (60 °C). If the operating temperature of 60 °C is not achieved, the duration of the sealing process may extend accordingly (by several days).
4. It is essential to ensure that the circulating pump operates continuously during the sealing process, because the sealant can only reach the damaged area by circulation.
5. Fully open thermostatic valves.
6. Shake Liquid Micro well and add undiluted via the heating filling valve into the heating circuit (1 litre of sealant to 100 litres of water) – see „dosing instruction“.
7. Thoroughly vent circulating pumps and radiators.
8. After a minimum of 24 hours, the gas-fired boiler system can be placed back into normal operation (filters and strainers must be reinstalled).
9. In order to prevent undesirable crystallisation, all working equipment and objects, which have come into contact with the liquid sealants, must be rinsed thoroughly with water.
10. After 4 weeks the gas-fired boiler system must be flushed and filled with fresh water
| Hierarchy type: | variant |
|---|---|
| Product type: | M |
| Series: | LID |
| Net weight: | 2,49 kg |
geboliquid
geboliquid - two-component sealant for heating systems
geboliquid is an innovative silicate sealant based on silicates, developed to quickly and permanently seal leakages in the water-bearing parts of heating systems from the inside - without any time-consuming dismantling or drying work. The geboliquid Micro, S, L and XL variants are each tailored to the amount of water leakage: from a maximum of 10 litres per day (Micro) up to 800 litres per day (XL). This means that the right solution can be found for almost any size of damage. The product range is supplemented by geboliquid Clean, a cleaning concentrate for removing lime, rust and sludge from the heating system, and geboliquid Protect, an anti-corrosion agent in accordance with VDI 2035. Both products are compatible with common materials such as steel, aluminium, copper and plastics and ensure reliable and permanent operation of the system.
geboliquid is the practical solution for skilled tradespeople who want to repair heating systems economically and protect them sustainably at the same time.